T1 - Integrated projects planning in IS departments
T2 - A multi-period multi-project selection and assignment approach with a computerized implementation
AU - Chen, Chung Yang
AU - Liu, Heng An
AU - Song, Je Yi
N1 - Funding Information:
This paper thanks relevant stakeholders from XXXX (NTC) Company, especially Wesley Chang (Senior Director), Gary Chang (Department Manager), and Walker Chen (Section Chief) for their support and collaboration in the research. The authors thank the Taiwan National Science Council for financially supporting this research (100-2628-E-008-009-MY2).
PY - 2013/9/16
Y1 - 2013/9/16
N2 - This paper highlights the subject of integrated projects planning (IPP) in contemporary IS departments, and presents a multi-period, multi-project selection and assignment approach (MPPA) to assist the departments in handling continuous project-based IS requests. The MPPA features a model to optimize the selection and assignment of IS projects. In the scope of multi-project, multi-period planning, the model innovatively considers the losses due to (1) the accumulated postponement of a previously unselected IS request and (2) the expected delay of ongoing projects when inserting a new project request. The MPPA also features an event-based decisional process for cumulative selection and assignment on a multi-period basis. Due to the complex and contextual nature of data in this paper, a computerized system is implemented for aiding the execution of the model and the process. The paper reports on an industrial case for a demonstration of the proposed work. Finally the paper compares the MPPA with related work to summarize the value and role it may play in the IPP context.
AB - This paper highlights the subject of integrated projects planning (IPP) in contemporary IS departments, and presents a multi-period, multi-project selection and assignment approach (MPPA) to assist the departments in handling continuous project-based IS requests. The MPPA features a model to optimize the selection and assignment of IS projects. In the scope of multi-project, multi-period planning, the model innovatively considers the losses due to (1) the accumulated postponement of a previously unselected IS request and (2) the expected delay of ongoing projects when inserting a new project request. The MPPA also features an event-based decisional process for cumulative selection and assignment on a multi-period basis. Due to the complex and contextual nature of data in this paper, a computerized system is implemented for aiding the execution of the model and the process. The paper reports on an industrial case for a demonstration of the proposed work. Finally the paper compares the MPPA with related work to summarize the value and role it may play in the IPP context.
KW - Information system (IS) development projects
KW - Mixed integer programming
KW - Multi-project multi-period
KW - Project management
KW - Projects selection and assignment
UR - http://www.scopus.com/inward/record.url?scp=84877694003&partnerID=8YFLogxK
U2 - 10.1016/j.ejor.2013.02.057
DO - 10.1016/j.ejor.2013.02.057
M3 - 期刊論文
AN - SCOPUS:84877694003
SN - 0377-2217
VL - 229
SP - 683
EP - 694
JO - European Journal of Operational Research
JF - European Journal of Operational Research
IS - 3
ER -