An empirical study of schedule delay causes based on Taiwan's litigation cases

Jyh Bin Yang, Mei Yi Chu, Kuei Mei Huang

研究成果: 雜誌貢獻期刊論文同行評審

24 引文 斯高帕斯(Scopus)

摘要

Many uncertainties can cause construction projects to be delayed, resulting in conflicts between the two parties to a construction contract. Using case study and content analysis methodologies, this study analyzed 79 litigation cases in Taiwan to identify the main causes of schedule delays in construction projects, which are "change orders," "changed scope of the work," "delayed site handover," and "weather." In this study, these causes are organized into a causation model to provide a reference for preventing schedule delay. The employed approach can be implemented for assessments of other regions, as schedule delays are common features in most construction projects.

原文???core.languages.en_GB???
頁(從 - 到)21-31
頁數11
期刊Project Management Journal
44
發行號3
DOIs
出版狀態已出版 - 6月 2013

指紋

深入研究「An empirical study of schedule delay causes based on Taiwan's litigation cases」主題。共同形成了獨特的指紋。

引用此