Production scheduling and truck dispatching of ready mixed concrete

Shangyao Yan, Weishen Lai, Maonan Chen

Research output: Contribution to journalArticlepeer-review

73 Scopus citations

Abstract

In this research, we develop an integrated model that combines ready mixed concrete (RMC) production scheduling and truck dispatching in the same framework. The model is formulated as a mixed integer network flow problem with side constraints, which is characterized as NP-hard. To solve realistic problems, we develop a solution method, which incorporates a mathematical programming solver. To evaluate the model and the solution method, numerical tests using real operating data from an RMC firm in Taiwan are performed. The test results show that the model and the solution algorithm would be useful for actual operations.

Original languageEnglish
Pages (from-to)164-179
Number of pages16
JournalTransportation Research Part E: Logistics and Transportation Review
Volume44
Issue number1
DOIs
StatePublished - Jan 2008

Keywords

  • Network flow problem with side constraints
  • RMC truck
  • Ready mixed concrete
  • Scheduling
  • Time space network