Do too many goals impede a program? A case study of enterprise system implementation with multiple interdependent projects

Jamie Y.T. Chang, James J. Jiang, Gary Klein, Eric T.G. Wang

Research output: Contribution to journalArticlepeer-review

21 Scopus citations

Abstract

Complex or large information technology (IT) implementations are typically managed as single programs composed of multiple projects. Program managers must be able to manage the interfaces of multiple interdependent projects to realize the goals of an IT implementation. However, the common problems of conflict and poor coordination often hinder the achievement of a program's goals. Part of this difficulty may lie in the structuring of the program goals themselves. Guided by Strategic Consensus Theory (SCT) and Realistic Group Conflict Theory (RGCT), we examine three enterprise system programs to study the relationship between the shared understanding of multiple or single program goals and conflict resolution and the coordination of programs in an attempt to explain a program's successful implementation. We find that a shared goal understanding as suggested by SCT is not sufficient to facilitate essential coordination. However, a superordinate goal as suggested by RGCT appears to resolve any discrepancies. The results imply that goals should be structured as superordinate requirements.

Original languageEnglish
Pages (from-to)465-478
Number of pages14
JournalInformation and Management
Volume51
Issue number4
DOIs
StatePublished - Jun 2014

Keywords

  • Conflict resolution
  • Enterprise system implementation
  • Program management
  • Realistic group conflict
  • Strategic goal consensus