Applying building information modeling to integrate schedule and cost for establishing construction progress curves

Kun Chi Wang, Wei Chih Wang, Han Hsiang Wang, Pei Yuan Hsu, Wei Hao Wu, Cheng Ju Kung

Research output: Contribution to journalArticlepeer-review

38 Scopus citations

Abstract

A cost-based progress curve (called S-curve) is often used to control construction project schedules. To establish a progress curve, the costs that are associated with each scheduling activity must be determined. However, the distributions of the quantities (costs) of cost items among various activities are time-consuming to obtain and error-prone, yielding an unreliable S-curve. This work proposes the use of three-dimensional building information model (BIM) objects to integrate schedule and cost by using the powerful BIM for data acquisition and storage. BIM objects are incorporated into a proposed four-step model to establish construction progress curves. The proposed model defines search criteria (cost item, object, floor, and zone) that precisely identify takeoff objects for extracting the quantities of cost items associated with each activity. The BIM uses keynote, assembly code, and family type catalog functions to provide pop-up menus for the efficient identification of cost items that are associated with each object to preventing errors in the manual typing of cost-item names. Finally, this work demonstrates that uploading the cost items and unit prices into cost estimation software in advance is critical to automating cost estimations in BIM.

Original languageEnglish
Pages (from-to)397-410
Number of pages14
JournalAutomation in Construction
Volume72
DOIs
StatePublished - 1 Dec 2016

Keywords

  • Building information modeling
  • Progress curves
  • Quantity takeoffs
  • Scheduling, activity cost

Fingerprint

Dive into the research topics of 'Applying building information modeling to integrate schedule and cost for establishing construction progress curves'. Together they form a unique fingerprint.

Cite this